The collaboration with Cor Verkolf was characterized by efficiency and effectiveness. Throughout the quotation phase, Cor Verkolf adapted quickly and responded directly to Bunzl’s needs. Notably, the tight 12-week schedule was not only met but exceeded. The approximately 30,000m2 area was realized in just 10 weeks, from project initiation to completion.
“Cor Verkolf has its own production in the Netherlands, including dedicated personnel for work shifts,” states Henk. “This capability facilitated the quick delivery. We also made excellent arrangements for partial handovers. The project was delivered in three phases, allowing us to commence further preparations in between deliveries. Weekly meetings were held to discuss progress and address any issues. If you seek a reliable partner in pallet supplying, I can certainly recommend Cor Verkolf. They provided significant support and streamlined our operations.”